RentServers GPU & Colocation Market Report · November 16, 2026

H100 at $3.93 an hour: the GPU and colocation market this week

Weekly GPU rental prices, colocation and power news, and what they mean for infrastructure buyers, every figure sourced and dated.

By the RentServers.com infrastructure desk · Data window November 9, 2026 to November 15, 2026 · PDF

Market summary

GetDeploying's H100 on-demand median was $3.93 per GPU-hour in the week of November 9, 2026, across 44 providers, down 0.3% from the week before and up 12.3% over four weeks.1 GetDeploying's B200 on-demand median was $8.13 per GPU-hour in the week of November 9, 2026, across 23 providers, up 1.5% from the week before and up 1.8% over four weeks.2

TrendForce (November 11, 2026): Against this backdrop, some manufacturers are planning to adjust memory procurement for 4Q26, and even 1Q27, while considering a greater reliance on private-label models in their shipment mix.3

As coal burn declines, rising power demand will be primarily met by renewables: EIA. The electric power sector could install more than 26 GW of battery storage next year, helping support a renewable resource base that is expected to supply almost a quarter of 2027 consumption, EIA said.4

GPU pricing this week

GetDeploying's H100 on-demand median was $3.93 per GPU-hour in the week of November 9, 2026, across 44 providers, down 0.3% from the week before and up 12.3% over four weeks.1 The H100 12-month reserved median was $3.21 per GPU-hour in the week of November 9, 2026.5

GetDeploying's H200 on-demand median was $5.00 per GPU-hour in the week of November 9, 2026, across 35 providers, unchanged from the week before and up 2.5% over four weeks.6 The H200 12-month reserved median was $3.89 per GPU-hour in the week of November 9, 2026.7

GetDeploying's B200 on-demand median was $8.13 per GPU-hour in the week of November 9, 2026, across 23 providers, up 1.5% from the week before and up 1.8% over four weeks.2 The B200 12-month reserved median was $7.68 per GPU-hour in the week of November 9, 2026.8

GetDeploying's B300 on-demand median was $9.50 per GPU-hour in the week of November 9, 2026, across 17 providers, unchanged from the week before and up 5.7% over four weeks.9 The B300 12-month reserved median was $6.59 per GPU-hour in the week of November 9, 2026.10

GetDeploying's MI300X on-demand median was $2.87 per GPU-hour in the week of November 9, 2026, across 5 providers, up 0.3% from the week before and down 35.1% over four weeks.11 The MI300X 12-month reserved median was $2.07 per GPU-hour in the week of November 9, 2026.12

As a second source: Price of Compute's on-demand median for H100 SXM was $3.99 per GPU-hour on November 16, 2026, across 9 providers.13 Price of Compute's on-demand median for B200 was $8.60 per GPU-hour on November 16, 2026, across 5 providers.14 Price of Compute's on-demand median for B300 was $6.60 per GPU-hour on November 16, 2026, across 3 providers.15

H100H200B200B300

On-demand median by GPU, USD per GPU-hour, last 12 weeks$0.00$2.50$5.00$7.50$10.0008/2409/1410/0510/2611/09H100, 08/24: $3.37H100, 08/31: $3.32H100, 09/07: $3.34H100, 09/14: $3.34H100, 09/21: $3.38H100, 09/28: $3.38H100, 10/05: $3.49H100, 10/12: $3.50H100, 10/19: $3.71H100, 10/26: $3.83H100, 11/02: $3.94H100, 11/09: $3.93H200, 08/24: $4.38H200, 08/31: $4.40H200, 09/07: $4.40H200, 09/14: $4.44H200, 09/21: $4.44H200, 09/28: $4.50H200, 10/05: $4.63H200, 10/12: $4.88H200, 10/19: $5.00H200, 10/26: $4.88H200, 11/02: $5.00H200, 11/09: $5.00B200, 08/24: $6.37B200, 08/31: $6.01B200, 09/07: $6.25B200, 09/14: $6.52B200, 09/21: $6.49B200, 09/28: $6.79B200, 10/05: $6.79B200, 10/12: $7.99B200, 10/19: $7.99B200, 10/26: $7.99B200, 11/02: $8.01B200, 11/09: $8.13B300, 08/24: $7.87B300, 08/31: $7.89B300, 09/07: $7.89B300, 09/14: $7.87B300, 09/21: $7.89B300, 09/28: $8.62B300, 10/05: $8.99B300, 10/12: $8.99B300, 10/19: $8.99B300, 10/26: $9.15B300, 11/02: $9.50B300, 11/09: $9.50$9.50B300$8.13B200$5.00H200$3.93H100
Provider medians by week (latest complete week: November 9, 2026). Data: GetDeploying GPU price history, CC BY 4.0. Chart drawn from the data, not generated.
This week's on-demand median, USD per GPU-hourH100H100: $3.93$3.93H200H200: $5.00$5.00B200B200: $8.13$8.13B300B300: $9.50$9.50MI300XMI300X: $2.87$2.87
Week of November 9, 2026. Data: GetDeploying, CC BY 4.0.

Colocation and power

As coal burn declines, rising power demand will be primarily met by renewables: EIA. The electric power sector could install more than 26 GW of battery storage next year, helping support a renewable resource base that is expected to supply almost a quarter of 2027 consumption, EIA said.4

Data centers could lower your electricity bill. Will utilities let them?16

PJM Accepts Fourth Expedited Interconnection Track Project. In October, PJM accepted the first three proposals: two battery storage projects and one natural gas generator upgrade with more than 2,100 MW in combined nameplate capacity. […]17

Deals and announcements

Developer Westend Real Assets buys two data centers in Hamburg.18

AirTrunk signs MoU for 1.8GW of data center capacity in Andhra Pradesh, India.19

European Union offers to build data center for Moldova.20

Sponsored: When the pressure heats up, what really cools servers down?21

Integrated data center infrastructure.22

Labor Shortages Threaten Data Center Schedules.23

What it means for buyers

My take: rental prices are still moving up, so if you have a renewal or a new cluster in the next quarter, get counter-quotes now and ask for multi-year terms with a price lock.1

My take: memory and flash costs feed straight into server and GPU node prices. Budget for higher hardware quotes into next year.3

My take: power, not floor space, sets colocation timelines. Ask every facility for the energized date and committed kW per rack in writing.4

Get counter-quotes

Make 3+ providers bid for your servers. Send your spec, invoice or renewal notice and get three or more quotes normalized into one 36-month cost within one business day. Suppliers see your name and company only after you consent to registration.

Get counter-quotes or call (312) 313-3883.

Sources

  1. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  2. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  3. TrendForce, November 11, 2026. trendforce.com
  4. Utility Dive, November 12, 2026. utilitydive.com
  5. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  6. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  7. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  8. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  9. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  10. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  11. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  12. GetDeploying (CC BY 4.0), November 9, 2026. getdeploying.com
  13. Price of Compute, November 16, 2026. priceofcompute.com
  14. Price of Compute, November 16, 2026. priceofcompute.com
  15. Price of Compute, November 16, 2026. priceofcompute.com
  16. Utility Dive, November 12, 2026. utilitydive.com
  17. PJM Inside Lines, November 10, 2026. insidelines.pjm.com
  18. DatacenterDynamics, November 14, 2026. datacenterdynamics.com
  19. DatacenterDynamics, November 14, 2026. datacenterdynamics.com
  20. DatacenterDynamics, November 14, 2026. datacenterdynamics.com
  21. DatacenterDynamics, November 14, 2026. datacenterdynamics.com
  22. DatacenterDynamics, November 13, 2026. datacenterdynamics.com
  23. Data Center Knowledge, November 13, 2026. datacenterknowledge.com

Opinions marked "My take" are the author's. Figures are as published by each source on the date shown; forecasts are labeled. Not investment advice.